![]() |
|||
![]() |
Home > Sewage Disposal > Greywater Sumps |
||
|
A Guide to Greywater Sumps |
|||
|
SUMP/ABSORPTION BED
Maximum bed depth = 4'
TOTAL CUBIC FEET = 96 (which is equal to 104 square feet of sidewall area and bottom of trench)
These dimensions can be altered as needed as long as the total trench depth below the ground surface does not exceed 5 feet. Shallow narrow trenches are preferred. There are three steps to properly completing a gray-water sump. 1) Determine its location and
size; 2) Apply for and obtain an approved permit from our office; and, 3) Install the sump and
obtain a final inspection by our office.
1) LOCATING AND SIZING THE SUMP The size of the sump depends on the amount of wastewater and the ability of the soil to absorb
water. County wastewater disposal code requires that a sump have (for washing machine effluent
only) a total volume of at least 96 cubic feet. The sump size for other sources of wastewater
must be calculated based on the amount of daily water use of the household. For average
draining soils allow one square foot of combined sidewall and trench bottom per gallon of
wastewater loading per day. Call our office for assistance in properly sizing the sump if needed.
When determining the proper location for the sump, the following standards and minimum
setbacks must be met:
septic tank 3 feet leach-field 10 feet property line 5 feet foundation 5 feet water line (pipe) 10 feet well 100 feet embankment >67% twice the height of the embankment up to 25 feet. stream 50 feet drainage way 25 feet
Other standards: geologic hazard a sump CANNOT be placed in a location where it may contribute to geologic instability groundwater separation vertical distance below the sump to groundwater must be at least 1 foot if the sump is at least 100 feet from a stream, creek, spring, or other body of water. If the sump is less than 100 feet, a 3 foot groundwater separation is required. minimum cover 1 foot maximum depth from surface 5 feet
2) SUBMITTING AN APPLICATION A plot plan must be submitted with an application form and a non-refundable fee is charged at
this time. The following information must be included on the plot plan:
Property lines and adjacent streets, footprint of the house, garage, other structures Existing septic system, however much is known Large trees, fences, etc. Wells, streams, drainage ways, springs Indicate all setback distances as described above
3) INSTALLATION & APPROVAL Once the district Registered Environmental Health Specialist
(REHS) has reviewed and
approved the application and the permit is issued, work may begin on the sump. You must notify
the REHS 24 hours prior to beginning the work. When the sump is filled and plumbed, but not
yet covered, the REHS will visit the site to approve and sign off the installation.
|
|||
|
|
|||
|
|
|||